Saturday, December 4, 2010

Friday, November 12, 2010

Dismantle of Old G.I Pipes at Block D

Please be informed that the contractor will be dismantling the old G.I Pipe from the Water Riser Room.

They will some hacking at the water riser room to dismantle the pipes easily. During this period there will be no disruption to water supply.

The schedule of work is as follows:-

DATE       :  12/11/10,15/11/10,16/11/10,18/11/10
TIME        :  9.00 AM to 5.00 PM

Our technicians will be present to monitor the works.

Your co-operation on the above matter is much appreciated. We regret for any inconvenience caused.

The Management 
9th November 2010

Dismantle of Old G.I Pipes at Block C

Please be informed that the contractor will be dismantling the old G.I Pipe from the Water Riser Room.

They will some hacking at the water riser room to dismantle the pipes easily. During this period there will be no disruption to water supply.

The schedule of work is as follows:-

DATE       :  16/11/10,18/11/10,19/11/10,22/11/10
TIME        :  9.00 AM to 5.00 PM

Our technicians will be present to monitor the works.

Your co-operation on the above matter is much appreciated. We regret for any inconvenience caused.

The Management 
9th November 2010

Tuesday, November 9, 2010

Dismantle of Old G.I Pipes at Block B

Please be informed that the contractor will be dismantling the old G.I Pipe from the Water Riser Room.

They will some hacking at the water riser room to dismantle the pipes easily. During this period there will be no disruption to water supply.

The schedule of work is as follows:-

DATE       :  15/11/10,16/11/10,18/11/10,19/11/10
TIME        :  9.00 AM to 5.00 PM

Our technicians will be present to monitor the works.

Your co-operation on the above matter is much appreciated. We regret for any inconvenience caused.

The Management 
9th November 2010

Wednesday, November 3, 2010

Dismantle of Old G.I Pipes at Block A

Please be informed that the contractor will be dismantling the old G.I Pipe from the Water Riser Room.

They will some hacking at the water riser room to dismantle the pipes easily. During this period there will be no disruption to water supply.

The schedule of work is as follows:-

DATE       :  9/11/10 – 12/11/10
TIME        :  9.00 AM to 5.00 PM

Our technicians will be present to monitor the works.

Your co-operation on the above matter is much appreciated. We regret for any inconvenience caused.

The Management 
3rd November 2010

Monday, October 11, 2010

Replacing New Water Pipe at Block D

Please be informed that the contractor will be replacing new water
pipes at roof tank and water meter riser room located at every
floor. The contractors will also be washing the water tank at roof
top.

The time period required to disconnect the old water pipes and to
replace with new water pipes is 30 hours which includes time to dry
the pipe glue. During this period there will be disruption to water
supply at Block D for 30 hours.

The contractor will be working throughout this period to speed up
the piping works.

The total work schedule for the above works is as follows:-

13/10/10 (Wed) 10AM – 14/10/10 (Thu) 4PM

Our technicians will be present to monitor the works.

We advice all residents to store water for their own use during
the above works.

Your co-operation on the above matter is much appreciated. We
regret for any inconvenience caused.

The Management
7th October 2010

Friday, October 1, 2010

Replacing New Water Pipe at Block C

Please be informed that the contractor will be replacing new water
pipes at roof tank and water meter riser room located at every
floor. The contractors will also be washing the water tank at roof
top.

The time period required to disconnect the old water pipes and to
replace with new water pipes is 30 hours which includes time to dry
the pipe glue. During this period there will be disruption to water
supply at Block C for 30 hours.

The contractor will be working throughout this period to speed up
the piping works.

The total work schedule for the above works is as follows:-

06/10/10 (Wed,10AM) – 07/10/10 (Thu,4PM)

Our technicians will be present to monitor the works.

We advice all residents to store water for their own use during
the above works.

Your co-operation on the above matter is much appreciated. We
regret for any inconvenience caused.

The Management
1st October 2010

Friday, September 24, 2010

Replacing New Water Pipe at Block B


Please be informed that the contractor will be replacing new water
pipes at roof tank and water meter riser room located at every
floor. The contractors will also be washing the water tank at roof
top.

The time period required to disconnect the old water pipes and to
replace with new water pipes is 30 hours which includes time to dry
the pipe glue. During this period there will be disruption to water
supply at Block B for 30 hours.

The contractor will be working throughout this period to speed up
the piping works.

The total work schedule for the above works is as follows:-

29/9/10 (10AM) – 30/9/10 (4PM)

Our technicians will be present to monitor the works.

We advice all residents to store water for their own use during
the above works.

Your co-operation on the above matter is much appreciated. We
regret for any inconvenience caused.

The Management
23rd September 2010

Saturday, September 18, 2010

Replacing New Water Pipe at Block A


Please be informed that the contractor will be replacing new water
pipes at roof tank and water meter riser room located at every
floor. The contractors will also be washing the water tank at roof
top.

The time period required to disconnect the old water pipes and to
replace with new water pipes is 30 hours which includes time to dry
the pipe glue. During this period there will be disruption to water
supply at Block A for 30 hours.

The contractor will be working throughout this period to speed up
the piping works.

The total work schedule for the above works is as follows:-

21/9/10 (10AM) – 22/9/10 (4PM)

Our technicians will be present to monitor the works.

We advice all residents to store water for their own use during
the above works.

Your co-operation on the above matter is much appreciated. We
regret for any inconvenience caused.

The Management
17th September 2010

Saturday, May 15, 2010

New Lift Ceiling and Lights



The new lift ceiling can be viewed at Block B, bomba lift. Any feedback is welcome.

Friday, February 5, 2010

Completed Projects In Year 2009

There were two big projects completed recently in year 2009 - the Lift Maintenance Project and Lift Car CCTV Project.

The Lift Maintenance Project was awarded to SML, a lift engineering company. The scope of this project were to de-rust wire ropes, replace worn out main sheaves and governor ropes. Pictures below showing the derusting work.



The CCTV Project was tender awarded to Ektech Sdn. Bhd. This project is to install CCTV in all the lift cars. The project started on the 3rd November, 2009 and completed on the 8th December, 2009.

Sunday, January 24, 2010

Lift Refurbishment Project

The photos shown below are the types of material and design chosen for the Lift Refurbishing Project. The color and pattern might differ from our selection.

1. Mirror finish stainless steel ceiling with down lights

 



2. Tempered glass wall



3. Granite flooring



4. Spray paint landing doors at basement and ground floor lobbies.